Railway applications - Infrastructure - Acceptance of works - Part 5: Procedures for rail reprofiling in plain line, switches, crossings and expansion devices
Abstract
This document specifies the procedure for planning and execution of rail reprofiling work on track in service. It concerns work in both plain lines, and switches and crossings, generally done with machines according to the EN 14033 series and EN 15746 series. It applies to vignole railway rails of 46 kg/m and above according to EN 13674-1.
Begin
2026-02-05
WI
00256A62
Planned document number
DIN EN 13231-5
Project number
08701732
Responsible national committee
NA 087-00-01-12 UA - Monitoring and treatment of rails
Responsible european committee
CEN/TC 256/SC 1/WG 50 - Monitoring and treatment of rails